DEVELOPMENT PLANNING
October 06, 2025 919
Updated plans offer further details on the 1B and 1C buildings of Quayside
After the reporting of urbantoronto last week on the resumption of the Quayside repetition and the conversion 2 revisions, new documents for the approval of location plans were published for buildings 1b and 1c, whereby the latest revisions for the renovation in Torontos East Bayfront by Dream Unlimited gave additional revisions And Great golfIn cooperation with Waterfront Toronto. Together, the submissions promote the first phase of the construction phase of Quayside east of the Bonnycastle Street, in which a mixed tenure program is planned. The buildings would be surrounded by a new community forest and a planned community center.
View northwest into the revised design for Quayside, designed by Architects – Alliang, Henning Larsen Architects and Teeple Architects for Dream Unlimited, Great Golf and Waterfront Toronto
The blocks 1b and 1c occupy the southern and southwestern part of the 4.9 hectare Quayside country on the south side of the Lake Shore Boulevard East between the Bonnycastle Street and the Small Street, which extends south to Queens quay East. The assembled properties from 257 to 291 Lake Shore Boulevard East, 200 Queens Queens and 2 Small Street Cover approx. 2.8 hectares and are currently occupied by commercial and office buildings with low and office that are tied to the former industrial past in the location.
Location plan for phases 1 and 2, picture of the submission to the city of Toronto
Urban Strategies Inc. has submitted the latest applications to the city of Toronto on behalf of the developers. The latest documents offer more insights into details such as size, amenities and parking spaces.
Building 1b in Quayside, designed by Henning Larsen Architects for Dream Unlimited, Great Golf and Waterfront Toronto
Building 1b, designed by Henning Larsen Architects with architect alliang as an architect of Record, would increase by 66 floors (231.4 m), slightly larger than the 64-story, 228.2 million version of the submission of last year. The design contains 729 rental units from 816, divided into 553 market rentals and 176 affordable rentals. The equipment programming would be a total of 1,510 m² interiors (up of 917 m²) and 907 m² outdoors (around 281 m²) with landscape terraces with a view of the central community forest (around 281 m²).
Plan of the ground floor for Bau 1b, designed by Henning Larsen Architects for Dream Unlimited, Great Golf and Waterfront Toronto
Below the class are two levels of joint parking spaces for 202 vehicle rooms (184 long-term and 18 short-term) as well as 570 bicycle areas between 419 long-term and 151 short-term stands. The tower would include seven elevators that result in approximately one elevator per 104 units, which requires high -speed engines to provide acceptable response times. The mass of 1b was refined to create a slimmer vertical profile, which means that daylight access and open views in the adjacent pops (private in possession of publicly accessible space) are preserved.
Building 1b in Quayside, designed by Henning Larsen Architects for Dream Unlimited, Great Golf and Waterfront Toronto
In the meantime, building 1c, which was designed by Teple Architects with architects as an architect of the recording, now consist of two 13-story middle classes along the north side of the Queens Queen Ost along the length of the block. At 44.1 m, this is a minor withdrawal from the 12-story version of 49.20 m in 2024. The additional store counter reflects the use of the amenities in the mechanical penthouse level. (Urbantoronto counts all floors that are accessible to building users/residents and visitors.)
Building 1c in Quayside, designed by Teple Architects for Dream Unlimited, Great Golf and Waterfront Toronto
Together, the 1C buildings contain 377 affordable rental units, with the total units of 463 previously decreased. However, they offer a higher proportion of family-sized suites that are now in 31 studios, 134 a bedroom, 148 two-room two rooms and 64 three-bedrooms or larger or larger. The equipment rooms would be a total of 497 m² indoors and 130 m² outdoors (of 566 m² and 606 m² in 2024), distributed over level 1, 7 and the mechanical penthouse.
Earth store plan for buildings 1c, designed by Teple Architects for Dream Unlimited, Great Golf and Waterfront Toronto
No vehicles for parking spaces have yet been provided for 1c, but 512 bicycle parking spaces are proposed, including 422 long-term and 76 short-term for residents as well as 6 long-term and 8 for short-term non-registrations. There would be six elevators in the 1C buildings, which led to a ratio of approximately one Pro 63 units. Although the construction of mass times is previously provided, the application explains that the relocation to conventional construction should simplify delivery, which means that a faster expansion and the higher proportion of affordable units in family size and at the same time maintain energy -efficient standards under Toronto Green Standard V4 Tier 1.
Niche in the building 1c in Quayside, designed by Teple Architects for Dream Unlimited, Great Golf and Waterfront Toronto
Both buildings 1b and 1c combine with a common two -story garage that serves the western part of Quayside and is accessible by Lake Shore Boulevard East. The terrain is served by the TTC bus service from the Union Station along Queens Queens Queens. The planned Waterfront East LRT, which was once financed and built, would improve the transit service in this corridor.
Updated community forest plan for quayside, picture of Dream Unlimited, Great Golf and Waterfront Toronto
A focus of development activity is in the East Bayfront. The blocks 3 and 4 from Quayside contain four additional towers of 12 to 72 floors. In the east, 307 Lake Shore East is proposed on 49 floors, while in 351 Lake Shore Ost Towers of 41 and 49 floors are planned. The recently completed Aqualina and Aquavista (13 floors), Aquabella (14 floors) and Aqualuna (18 floors) include south, Tridel and Hines' Bayside community. The construction in the 21-story Quay House is completed to the west and is underway for the first phase of Pinnacle Lakeside (towers from 15 to 54 floors), while a 43-story second phase is planned.
Urbantoronto will continue to follow progress in these developments. In the meantime, however, you can find out more about you from our database files linked below. If you want, you can join the conversations in the associated project forum threads or leave a comment on the storage space provided on this page.
* * *
The Urbantoronto, UtPro research and data service provides comprehensive data on construction projects in the Greater Golden Horseshoe – from the proposal to the end. Other services include instant reports, downloadable snapshots based on the location and a daily subscription newsletter, New Development Insider, which pursues projects from the first application.